Resilience Engineering #16: Hammering out a Schedule

by Gary Monti on October 4, 2011

Nailing down a schedule is one of the biggest project challenges there is. Even when you get it right things can happen in the environment that destabilize scheduling efforts. In a previous blog, Resilience Engineering #12: Party Time, the FRAM (Functional Resonance Accident Model) model was introduced as a way to provide rich contextual information for task definition and establishing a link between tasks. The phrase, “hammering out a schedule,” aptly implies the effort it takes to get one’s project house in order and determine who will do what and when.

Presently I am working with a client who wants a scheduling system. Before that can be done there is a lot of political house cleaning needed, which is the current focus of work. The hook being used to get them to stop gossiping and put that time and energy into work is shown in the diagram below.

What we have here is a FRAM diagram. The goal is to show the dynamics at play and how they can be mapped out for a given situation. Each hexagon is a function. The attributes for each function are:

  • I (Input). Raw material or the output of a previous task needed to execute the activity.
  • O (Output). The measurable deliverable from the activity.
  • P (Preconditions). Environmental and contextual considerations which are needed for success to occur, e.g., “clear requirements,” is a precondition for “task generation” to be effective.
  • R (Resources). Classic project management resources, e.g., people, tools, etc.
  • T (Time). This can be either classic duration, e.g., two effort hours, or calendar time, e.g., one evening.
  • C (Control). The parameters for setting acceptance criteria as well as process requirements that insure an adequate job is done.

The focus with the client is on the variable “preconditions.” It is an eye-opening exercise when looked at from the perspective of where the organization needs to be in order to support execution of a task.

The short version of this is 4-5 months of organizational work is needed before credible scheduling of the first task can begin. This is a group of engineers, technicians, accountants, sales people, and management having to do the touchy-feely work needed to communicate clearly and simply with committed support and follow-up.

Instead of “Hammering Out A Schedule,” it might have been better to title this “Hammering Out A Company.” Just to get to where a single task can be scheduled with high reliability it will be performed adequately within time and budget constraints almost the entire company is being profiled psychologically. Why? They can’t talk. They are technical experts. They can yell, they can be passive aggressive, they can be fearful, they can be greedy but they are very unskilled at understanding each other and are afraid of being honest and trusting.

We are making progress. It is stressful. They are uncomfortable. They are looking at those dark places from which strange noises emanate (better know as bitching and gossiping) and deciding what to do. All this before a single task can be scheduled with confidence.

Hammering out a schedule is hard work but well worth the effort. They are starting to see the benefits of putting energies into getting things done as a team rather than pointing fingers.

The court is out as to whether or not success will occur. This work reaches all the way into the Board Room. If they make it, though, they’ll be able to schedule a task and rely on the forecast. They’ll be able to go home and say, “I DID something constructive today and it feels good.”